That is the aspiration and determination of the officers and employees of the EVNNPC shock teams currently present at the construction sites of the 500kV circuit 3 power line project.
With the spirit of "All for the 500kV circuit 3 transmission line project," Hanoi Power Corporation (EVNHANOI) mobilized nearly 200 personnel to support this key project.
The 110kV transmission line from Pho Cao 220kV Substation to Hung Ha 110kV Substation was energized three months ahead of schedule, demonstrating EVNNPC's determination to successfully complete its assigned tasks.
In late April, the intense heat caused nationwide electricity consumption to reach record highs, with total consumption on April 26th reaching 993,974 million kWh.
Chào mừng kỷ niệm 70 năm ngày truyền thống ngành Điện lực Việt Nam, EVN tổ chức cuộc thi ảnh nghệ thuật với chủ đề "EVN - 70 năm đổi mới cùng đất nước".
On the afternoon of April 1st, Prime Minister Pham Minh Chinh chaired a meeting with ministries, departments, localities, and units regarding the 500kV circuit 3 power line project, section from Quang Trach to Pho Noi.
According to the draft, EVN will be allowed to decide on electricity price increases or decreases of less than 5%. If the increase is between 5% and less than 10%, the Ministry of Industry and Trade will issue a document approving the decision for EVN to make.
Vietnam Electricity Group (EVN) will continue to exploit and commercially operate the Phu My 3 BOT power plant (Ba Ria-Vung Tau province) from March 1, 2024.
Nhắc đến vụ án liên quan đến kinh doanh điện, Trung tướng Tô Ân Xô cho biết, loại “virus Việt Á biến thể” này tương đối phổ biến, Bộ Công an sẽ có vaccine điều trị.
Assigning tasks to EVN, the Prime Minister emphasized that there must be absolutely no electricity shortage for production, business, and consumption under any circumstances.
Many localities have not yet approved the policy on changing the land use purpose of planted forests as required by regulations, which is necessary for implementing compensation and land clearance work.
The government has submitted to the National Assembly Standing Committee a plan to allocate over 2.500 trillion VND to EVN from the central government budget to implement the project of bringing the power grid to Con Dao Island.
Mr. Tran Ngoc Linh, former Director, and Mr. Nguyen Thanh Ngon, Director, have been prosecuted in the case involving Tuan An Group Joint Stock Company and Binh Thuan Power Company.
The conclusion of the Government Inspectorate clearly indicates that EVN Group failed to complete the investment in the power grid as assigned, and failed to complete the planning for thermal power plants.
The Prime Minister instructed the Minister of Industry and Trade to direct the mobilization of the highest level of human resources to finalize and submit the mechanism for direct electricity trading to the competent authorities before December 31st.
At the conference summarizing the work of the industry and trade sector in 2023 and outlining tasks for 2024 on the morning of December 20th, the concern about electricity shortages was raised by local representatives.
EVN has requested the Ministry of Industry and Trade to appraise and submit to the Prime Minister a proposal to import electricity from the Truong Son wind power plant.
Two BOT gas-fired power plants, invested in by foreign companies, are nearing the date of transfer to the Vietnamese side after their 20-year contracts expire, and EVN has been assigned to take over.
Mr. Nguyen Danh Son, Director of the Electricity Trading Company (Vietnam Electricity Group - EVN), has been prosecuted for "Abusing his position and authority while performing his official duties".
The Security Investigation Agency of the Ministry of Public Security has initiated legal proceedings and arrested five officials from the Vietnam Electricity Group (EVN) and the Ministry of Industry and Trade on charges of abusing their positions and authority.
The Prime Minister approved the policy and accepted the investor for the 500kV transmission line project connecting Nam Dinh I Thermal Power Plant to Thanh Hoa, aiming to supplement the power supply for the North.
According to the Electricity Regulatory Authority (Ministry of Industry and Trade), the structure of Vietnam's power sources has undergone significant changes, with EVN now holding only about 37% of the electricity supply.
The State Capital Management Committee at Enterprises proposed disciplinary action in the form of a reprimand against the leaders of EVN and three leaders of the National Power System Dispatch Center.
The lack of mechanisms and real authority has led to operational stagnation and difficulties, according to representatives of the State Capital Management Committee at enterprises.
Deputy Prime Minister Tran Hong Ha has just issued directives on the plan to ensure electricity supply for production, business and people's consumption in the last months of 2023 and in 2024.
All personnel and two ODA loan repayments totaling nearly $3 million for the National Power System Dispatch Center will be transferred from EVN to the State Capital Management Committee.